Oracle Declares Force Majeure on Blue Owl New Mexico Data Centre

A force majeure notice from Oracle to a Blue Owl unit over power delays at a New Mexico data centre sent both stocks lower, raising questions about AI capacity contracts.

Matthew Ives 6 min read
High-voltage substation equipment and transmission lines next to a large data centre building

Oracle issued a force majeure notice to a Blue Owl unit developing a large data centre in New Mexico, citing delays in securing power for the project, a person familiar with the matter told BNN Bloomberg; ORCL fell 3.22% to 139.91 and OWL fell 4.90% to 9.13 as of 19:21 GMT on Sept. 24, 2026.

Oracle (ORCL) has sent a force majeure notice to a Blue Owl (OWL) unit that is developing a large data centre in New Mexico, citing delays in securing power for the site, according to a person familiar with the matter cited by BNN Bloomberg. It is a narrow contractual step with unusually wide implications, because it lands at the intersection of two things the market has been pricing aggressively: the pace of Oracle's artificial-intelligence capacity buildout, and the private-credit machinery that has been financing the buildings it goes into.

Markets took the point immediately. Oracle traded at 139.91, down 3.22% from a prior close of 144.56, with a session range of 133.48 to 140.35 as of 19:21 GMT on Sept. 24, 2026. Blue Owl traded at 9.13, down 4.90% from 9.60, in a range of 9.02 to 9.51. Both moves stand out against a flat tape: the S&P 500 proxy SPY was at $767.64, down 0.02%, and the Nasdaq 100 proxy QQQ at $741.02, down 0.03%, with the Dow proxy DIA off 0.34% at $512.56.

What a force majeure notice actually does

Force majeure is the clause in a commercial contract that suspends or excuses a party's obligations when an event outside its reasonable control prevents performance. It is not the same as a termination, and it is not by itself a claim of breach by the counterparty. In development contracts for large facilities, it typically buys time: deadlines stop running, delay damages may not accrue, and in some drafting it eventually opens a walk-away right if the condition persists long enough.

The facts disclosed here are limited and worth stating plainly. Oracle issued the notice. The recipient is a Blue Owl unit that is developing the New Mexico project. The stated reason is delay in securing power. The information comes from an unnamed source. Nothing in the lead establishes that the project has been cancelled, that a termination right has been exercised, or that any party has quantified a financial impact.

Still, the identity of the sender is what makes this notable. In a typical hyperscale arrangement, the tenant is the party waiting on the developer. A notice flowing from the customer's side toward the developer signals that the schedule, and the obligations tied to it, are being formally reset rather than quietly renegotiated.

Why power, not steel or chips, is the binding constraint

Data centre construction has moved through a sequence of bottlenecks over the last few years — land, then shells, then accelerators, then transformers and switchgear. The constraint that has proved hardest to engineer around is interconnection: the utility studies, queue positions, substation work and transmission upgrades required before a campus can draw the load it was designed for. That process runs on regulatory clocks, not construction schedules, and it does not accelerate because a tenant needs racks energized.

That is the category of problem that force majeure clauses were drafted for, and it is also why a dispute over it is rarely clean. Whether a grid interconnection delay counts as outside a developer's reasonable control depends on what the contract says, what commitments were made about energization dates, and what each side did to procure capacity. Those are the questions lawyers on both sides will now be working through.

The financing question sitting underneath the building

Blue Owl is an alternative asset manager whose franchise includes lending against and investing in exactly this kind of asset — long-duration, contracted infrastructure underwritten on the credit quality of a large corporate tenant. The economics of that model depend on the lease or development agreement being durable. If a tenant's obligations are suspended, the cash flows that a financing package was sized against become less certain, even temporarily.

The economics of that model depend on the lease or development agreement being durable.

That is the most plausible explanation for why Blue Owl's shares fell more in percentage terms on the day than Oracle's. Oracle's investors are weighing a schedule slip on one site within a much larger capacity programme. Blue Owl's investors are weighing what the episode says about the contractual protections embedded across data centre deals more broadly — and whether lenders and rating agencies will start attaching a discount to energization risk that was previously treated as a construction detail.

What to watch from here

  • Confirmation and scope. Neither company's formal characterisation of the notice is in the public record based on the reported facts. A filing, a statement, or a description on a coming earnings call would establish whether this is a schedule reset or the opening of a dispute.
  • The cure period. Force majeure clauses usually specify how long the condition can persist before other rights attach. The length of that window determines whether this is a quarter-long story or a structural one.
  • Read-across to other sites. If interconnection timing is the issue, it is unlikely to be confined to one campus. Watch whether other AI tenants adopt the same contractual posture.
  • Financing terms on new deals. Pricing, covenants and completion guarantees on the next round of data centre credit will show whether the market has repriced power risk.

The wider pattern this fits

The AI capacity trade has been underwritten on an assumption that demand is the scarce input and everything else can be bought. This notice is a reminder that the physical grid sets a floor on how fast compute can be delivered, and that the contracts strung between tenants, developers and lenders are where that friction eventually shows up as a number. Investors in Oracle should treat it as a timing question until the company says otherwise. Investors in Blue Owl, and in the broader private-credit complex lending to digital infrastructure, have a sharper question: how many other agreements contain the same clause, pointed at the same problem.

Key facts

  • ORCL price: 139.91, -3.22% (as of 19:21 GMT, Sept. 24, 2026)
  • OWL price: 9.13, -4.90% (as of 19:21 GMT, Sept. 24, 2026)
  • Action: Oracle issued a force majeure notice to a Blue Owl unit
  • Stated cause: Delays in securing power for a large New Mexico data centre

Frequently asked questions

What did Oracle do?

Oracle issued a force majeure notice to a unit of Blue Owl that is developing a large data centre in New Mexico. The notice cites delays in securing power for the project. The information was attributed to an unnamed person familiar with the matter and reported by BNN Bloomberg on Sept. 24, 2026.

What does force majeure mean in a contract?

Force majeure is a clause that suspends or excuses a party's contractual obligations when an event outside its reasonable control prevents performance. It typically pauses deadlines and may stop delay damages from accruing. It is not the same as terminating an agreement, though prolonged force majeure can trigger other rights depending on the drafting.

How did the shares react?

As of the last trade at 19:21 GMT on Sept. 24, 2026, Oracle (ORCL) was at 139.91, down 3.22% from a prior close of 144.56, in a range of 133.48 to 140.35. Blue Owl (OWL) was at 9.13, down 4.90% from 9.60, in a range of 9.02 to 9.51.

Was the broader market down that day?

No, the major benchmarks were close to unchanged. The S&P 500 proxy SPY traded at $767.64, down 0.02%, and the Nasdaq 100 proxy QQQ at $741.02, down 0.03%. The Dow proxy DIA was the weakest of the three at $512.56, down 0.34%, on the same timestamp.

Why is securing power such a problem for data centres?

Large campuses need utility interconnection — queue positions, system studies, substation work and sometimes transmission upgrades — before they can draw their designed load. That process moves on regulatory and utility timelines rather than construction schedules, so it cannot be accelerated simply because a tenant is ready to install equipment.

Does this mean the New Mexico project is cancelled?

Nothing in the reported facts establishes a cancellation. What is known is that Oracle issued a force majeure notice citing power delays. No termination, breach claim, or quantified financial impact has been reported. Investors would need a company statement, a regulatory filing, or earnings-call commentary to establish the project's status.