EXIM Puts Up to $6 Billion Behind Argentina's First LNG Export Plant
Washington's export credit agency has offered an indicative term sheet of up to $6 billion for a $51 billion Argentine LNG export scheme led by YPF, Eni and XRG.

The U.S. Export-Import Bank has issued a non-binding indicative term sheet worth up to $6 billion for the $51 billion Argentina LNG project led by YPF with Italy's Eni and Emirati firm XRG, the U.S. State Department said, under the newly launched Andes-Atlantic Corridor initiative.
The United States has put a number on its interest in Argentina's gas ambitions. The Export-Import Bank of the United States, the federal export credit agency known as EXIM, has issued a non-binding indicative term sheet of up to $6 billion for the Argentina LNG project, a $51 billion scheme to build the country's first liquefied natural gas export capacity, the U.S. Department of State said.
The project is led by Argentina's state-controlled energy group YPF in partnership with Italy's Eni and Emirati energy firm XRG. The EXIM offer sits inside a broader bilateral framework, the Andes-Atlantic Corridor, a joint U.S.-Argentinian initiative announced to strengthen and modernise infrastructure, under which U.S. government financing agencies can lend alongside private capital.
What a non-binding term sheet actually commits
The distinction matters. An indicative term sheet is not a loan. It sets out, on a preliminary basis, the size and shape of financing EXIM would consider — subject to due diligence, board approval, environmental review, and the sponsors reaching a final investment decision. Nothing has been drawn. Projects have received term sheets from export credit agencies and never closed.
What the document does do is change the conversation with every other lender in the room. Export credit agency participation is a signal to commercial banks and institutional debt investors that a sovereign-risk-heavy project has been screened by a government underwriter. For a project in Argentina — a country with a long record of capital controls, currency crises and restructured debt — that signal is worth more than it would be in, say, Qatar or Texas.
EXIM's mandate also explains the shape of the offer. The bank finances the purchase of American goods and services, not foreign construction generally. The State Department said the proposed financing is intended to support procurement of U.S. goods and services required for infrastructure development and production activities, specifically including the contract awarded to McDermott for the engineering, procurement, construction and commissioning of a natural gas liquids fractionation and gas treatment facility. In other words, the dollars are tied. They flow to the project only to the extent the project buys American.
The gap between $6 billion and $51 billion
Set against a total project cost of $51 billion, an EXIM facility of up to $6 billion would cover roughly 12% of the capital required — an illustrative share derived from the two figures disclosed. That leaves the overwhelming majority of the bill to be assembled from project sponsors' equity, commercial bank syndicates, bond markets, other export credit agencies and, potentially, offtake-linked prepayments from buyers.
That arithmetic is the real story for YPF. A company of its size cannot fund a $51 billion build from cash flow, and Argentina's sovereign borrowing costs have historically made local financing punishing. Every tranche that arrives with a government guarantee attached lowers the blended cost of the whole structure and shortens the distance to a final investment decision. Eni brings LNG marketing reach and liquefaction experience; XRG brings Gulf capital. EXIM's term sheet is the piece that was missing on the public-sector side.
It is also, plainly, a political result for Argentinian President Javier Milei, whose economic programme rests on attracting foreign investment into infrastructure. An American export credit facility of this scale is the kind of validation that Argentine administrations have spent years failing to secure. The full announcement was reported by Baystreet.
Why Argentina wants a liquefaction terminal at all
Argentina sits on one of the largest shale gas resources outside North America, in the Vaca Muerta formation. The constraint has never been geology; it has been geography and plumbing. Gas produced in Neuquén province has no route to a global buyer without liquefaction and a coastal export terminal. Domestic demand is seasonal and finite, and pipeline exports to neighbours are limited by the neighbours' own capacity to absorb them.
Argentina sits on one of the largest shale gas resources outside North America, in the Vaca Muerta formation.
Liquefaction changes the economics of every well drilled upstream. Once a producer can sell into the seaborne LNG market, gas that was previously stranded — or flared, or shut in during warm months — acquires an international price. That is why the project is described as Argentina's first LNG export project rather than simply another plant: it is the first link in a chain that would connect Vaca Muerta to Asia and Europe.
The natural gas liquids fractionation and gas treatment facility in the McDermott scope is part of that chain. Raw shale gas arrives with heavier hydrocarbons and contaminants that must be stripped out before the gas can be chilled to liquid. Fractionation separates those liquids into saleable products — an additional revenue stream in its own right — while treatment removes what would otherwise freeze or corrode inside a liquefaction train.
How the shares finished before the news
Market data as of the last trade on Wednesday, 23 September 2026 at 20:00 GMT shows both listed sponsors closed higher against a softer broad tape. YPF last traded at 53.93, up 1.09% on the day from a previous close of 53.35, with a session range of 52.99 to 55.60. Eni last traded at 54.83, up 2.95% from a previous close of 53.26, in a range of 53.93 to 54.97.
Those gains ran counter to the benchmarks. The S&P 500 tracker closed at $767.81, down 0.72%; the Nasdaq 100 tracker at $741.21, down 0.84%; and the Dow 30 tracker at $514.30, down 0.71%. Energy names outperforming a down day is not unusual, and the moves should not be read as a direct response to a term sheet — but they do frame the starting point from which investors will price the news.
What determines whether this gets built
Three things are worth watching. First, whether EXIM converts the indicative term sheet into an approved facility, and on what conditions — the bank's board process and any congressional notification requirements are the gating items. Second, whether the sponsors reach a final investment decision, which typically requires long-term offtake contracts signed with creditworthy buyers before a dollar of construction debt is drawn. Third, whether the Andes-Atlantic Corridor produces further financing commitments from other U.S. agencies, which would indicate the LNG facility is the first of a pipeline of deals rather than a one-off.
There is a fourth, less technical variable: Argentine politics. Export credit agencies underwrite decade-long construction and multi-decade repayment. The Milei administration's investment framework is what makes the numbers work today; whether it survives intact through the construction period is a risk lenders will price, and one no term sheet can eliminate.
Key facts
- EXIM indicative term sheet: Up to $6 billion, non-binding
- Total project cost: $51 billion
- Sponsors: YPF (lead), Eni, XRG
- YPF last close: 53.93, +1.09%, as of 23 Sep 2026 20:00 GMT
Frequently asked questions
What is the Argentina LNG project?
It is Argentina's first liquefied natural gas export project, a $51 billion development led by state-controlled energy group YPF in partnership with Italy's Eni and Emirati energy firm XRG. It would give Argentina's shale gas, produced inland, a route to international seaborne buyers by chilling it to liquid form for shipment.
How much is the U.S. lending and is it guaranteed?
The Export-Import Bank of the United States has issued a non-binding indicative term sheet for up to $6 billion. That is not a committed loan. It is a preliminary statement of the financing EXIM would consider, subject to due diligence, approvals and the sponsors reaching a final investment decision.
What is the Andes-Atlantic Corridor?
It is a newly launched joint U.S.-Argentinian initiative to strengthen and modernise infrastructure. Under the framework, U.S. government financing agencies can participate in funding Corridor projects alongside private sector capital. The State Department cited the LNG term sheet as an example in the energy infrastructure category.
Why is McDermott named in the announcement?
McDermott was awarded the contract for engineering, procurement, construction and commissioning of a natural gas liquids fractionation and gas treatment facility for the project. EXIM financing is designed to support procurement of U.S. goods and services, so American-scope contracts like this one are what the proposed facility would fund.
How did YPF and Eni shares finish most recently?
As of the last trade on 23 September 2026 at 20:00 GMT, YPF closed at 53.93, up 1.09% from a previous close of 53.35. Eni closed at 54.83, up 2.95% from 53.26. Both gained on a day when the S&P 500, Nasdaq 100 and Dow trackers all fell around 0.7% to 0.8%.
What share of the project cost would the EXIM facility cover?
Up to $6 billion against a stated $51 billion total works out to roughly 12% — an illustrative calculation from the two disclosed figures, not a reported financing structure. The remainder would need to come from sponsor equity, commercial lenders, bond markets, other export credit agencies and offtake-linked arrangements.